East Rutherford, New Jersey

Metlife Stadium Headend/Data Hub and DAS

Provided engineering and design services for the construction of a 2,035 SF Headend/Data Hub to support the new Distributed Antenna System (DAS) installed throughout Metlife Stadium. Total of 3 rows of 32 closed cabinets and 4 rows of 38 open telco racks.

Project also included 7 DC plants with a rooftop 300 KW backup generator, and 2 HVAC units each with a 60 ton cooling capacity. Distributed Antenna System (DAS) included 75 Wifi antennas and 142 radio units.

Services

Telecommunications Engineering and Design

Structural Engineering

Electrical Engineering

Million Square Feet
Million Square Feet
Million Square Feet
Million Square Feet

(Photo Credit: Nearmap)